THE CHALLENGE
An existing IHI shiploader, equipped with an 84-inch-wide belt conveyor handling 6,000 tons per hour of coal, was experiencing multiple operational problems:
- Frequent transfer chute plugging and excessive material spillage
- Belt misalignment resulting in premature belt damage
- Poor belt splice life and repeated re-splicing
- Insufficient gravity take-up travel
A comprehensive engineering evaluation identified several conveyor design deficiencies contributing to these ongoing problems.
THE ENGINEERED SOLUTION
Dos Santos International was contracted to provide complete, detailed engineering for a series of targeted improvements, including:
- Larger Pulleys: New pulleys incorporated into the conveyor upgrade.
- Take-Up System Improvements: An additional screw take-up system designed to reset available gravity take-up travel.
- Idler System Replacement: An entirely new garland idler structure.
- Transfer Chute Redesign: Improved material flow onto the shiploader boom conveyor.
- Material Containment Improvements: Belt-riding skirts and a redesigned convex curve over the boom hinge to help settle material onto the belt.
THE VALUE OF RETROFIT ENGINEERING
This project illustrates how a thorough engineering assessment can uncover the underlying causes of persistent conveyor problems and provide a practical path toward improved operation.
Rather than starting over, carefully engineered modifications can help operators address recurring maintenance issues, improve material handling, and extend the useful life of existing assets.